To price gutter installation, build a rate per foot from your own material cost, labor cost, overhead and profit. Then add downspouts, a higher rate for each story, removal of the old gutters and a job minimum. Measure the footage first, because every line depends on it. This guide works through each input on a sample house. The cost inputs are examples to replace with your own, not market prices.

A single-story home with its two front gutter runs marked along the roof edge and numbered.

Measure the footage

Gutters are priced on the roof edges that drain off the house. Measure each of those edges and add them up. Leave out edges that drain onto another roof, such as an upper roof that sheds onto a porch roof below. High upper edges that drain straight to the ground still count.

Keep runs on a lower roof separate. A porch or garage roof on a two-story house is a story lower, so it's quicker to reach and its downspouts are shorter. Pricing it at the lower story rate keeps the bid fair.

The sample house in this guide is a one-story home with a cross-gable roof. Measured Bid found 118 ft of gutter from aerial roof data, in 4 runs of 30, 20, 49, 20 ft.

118ftGutter footage, sample house
130 ft220 ft349 ft420 ft
The sample house. Each numbered run is a roof edge that drains off the house.

Build a per-foot rate

A per-foot rate has to cover four things: the material that goes on the house, your crew's time, your overhead and your profit.

Material per foot is everything that goes up with the gutter: coil, hangers, sealant, miters and end caps. Add up a normal job's material and divide it by that job's footage.

Labor per foot is your crew's cost per hour divided by the feet they hang per hour. Use loaded cost: wages plus payroll taxes, workers' comp and insurance. For a reference point, the Bureau of Labor Statistics reports a median wage of $29.71 an hour for sheet metal workers in May 2025, and it publishes wages by metro area. Time your own crew over a few jobs. Count setup, ladder moves and cleanup, and not only the minutes spent hanging gutter.

Overhead is the cost of running the company: trucks, the office, insurance, marketing and the time spent selling. Profit is what's left after that. Take both as a share of the price.

Material per foot (example)$3.50
Labor: 2 installers × $45.00/hr ÷ 30 ft/hr$3.00
Direct cost per foot$6.50
$6.50 ÷ (1 − 15% overhead − 20% profit)$10.00 / ft

Those example inputs land on $10.00 a foot, the one-story gutter rate Measured Bid uses as a sample. Your inputs will land somewhere else. That is the point: the rate should come from your costs.

Add a rate for each story

Higher gutters take longer. The crew needs taller ladders or staging, moves them more often and works slower at height. OSHA requires fall protection for residential construction work 6 feet or more above a lower level, and that adds setup time on every two-story job.

Measured Bid's sample rates add 20% for two stories and 50% for three or more. Start from your one-story rate and time a few two-story jobs to find your own step.

Sample rates in Measured Bid, per foot. Replace them with yours.
StoriesSeamless guttersGutter guards
1$10.00$15.00
2$12.00$18.00
3+$15.00$22.00

Count the downspouts

Price downspouts per downspout or per foot. Some contractors charge a set price for each downspout by story, usually a little less when it goes up with new gutters than on a downspout-only job. Either way, start with the count. If you price by the foot, the drop length decides the footage.

A count rule works for most bids: at least one downspout on each separate gutter, with one for every set number of feet or part of it and a minimum per job. The sample rule counts one per 35 ft or part of it on each separate gutter, and at least 2 per house. Each drop is about 10 feet per story plus 2 feet for elbows and the extension.

Separate gutters: one per 35 ft or part of it, at least 2 per house5
Downspout feet: 5 × (1 story × 10 ft + 2 ft)60 ft

The same house at two stories would need 110 ft of downspout. At a sample rate of $9.00 a foot, that difference alone is $450.00. A set price per downspout handles the same thing with a higher price for each story.

Sizing is a separate question from counting. Gutter and downspout size depend on roof area and how hard it rains where you work. SMACNA's Architectural Sheet Metal Manual has the method, and SMACNA's free gutter and downspout sizing calculator applies it.

Guards, removal and steep roofs

For maintenance work, use the gutter cleaning pricing guide to build a separate rate from crew time.

Gutter guards

Price guards per foot on the same footage as the gutters, with their own story rates. On a new-gutter job they cover the new runs. On a guards-only job they go on the existing gutters, so check that those gutters are sound before you quote.

Removing old gutters

Price tear-off per foot. It covers taking the old gutters down, hauling them away and disposal. The sample rate is $2.00 a foot.

Steep roofs

Steep roofs slow the crew even though the gutter hangs at the eave. Measured Bid adds a percent only to gutters and guards on roof sections over a pitch you pick. The sample adds 15% over 8/12.

Corners and returns

Roofs with many planes have more corners, miters and returns. Build them into your material per foot, or add an allowance on complex roofs. Measured Bid adds a small footage allowance when a roof has more than 6 guttered planes.

Set a job minimum

Every job has a fixed cost before the first foot goes up: the drive, loading, setup and cleanup. A minimum makes sure small jobs cover it. Set it near the price of the smallest job you'd take on a normal day.

Give guards-only jobs a separate minimum. They are often short add-ons. A 40 ft guards-only job at the sample rate of $15.00 a foot comes to $600.00. With the sample guards-only minimum of $800.00, the price is $800.00.

Worked example

Here is the sample house as a new-gutter job with guards, one story, with the old gutters removed, at the sample rates.

Sierra Gutter Co.

(916) 555-0100

Gutter estimate

No. 1042

Estimate forJordan Example412 Sample Ridge Ct, Roseville, CA
Sample rates
Stories
1 story
Job type
New gutters + guards
Steeper than 8/12
No
ItemQtyRateAmount
Seamless gutters118 ft$10.00 / ft$1,180.00
Gutter guards118 ft$15.00 / ft$1,770.00
Downspouts60 ft$9.00 / ft$540.00
Remove old gutters118 ft$2.00 / ft$236.00
Subtotal$3,726.00
Job minimum$1,000.00
Total$3,726.00

The lines add up to $3,726.00. In Measured Bid, the homeowner sees a range instead of one number, and the range widens when the roof data is less clear. For this house the homeowner sees $3,175 to $4,275, and your team sees the line items above.

Check your rates against won jobs

A rate is a guess until jobs come back. After each job, compare the footage you bid with the footage you installed, and the hours you planned with the hours the crew took. If one input is off on job after job, fix that input and leave the others alone.

Watch your close rate too. If you win nearly every bid, your rate may be low. If you lose most bids on two-story homes, look at your story step first.

Measured Bid's range accuracy report compares the sold price of won jobs with the range the homeowner saw, so you can tell whether your ranges are too tight or too wide.

FAQ

How much should I charge per foot for gutter installation?

Build the rate from your own costs: material per foot plus labor per foot, divided by one minus your overhead and profit shares. With the example inputs in this guide that comes to $10.00 a foot for one story. Your number depends on your material prices, your crew's speed and your overhead.

Should a two-story gutter job cost more per foot?

Yes. Taller ladders, fall protection and slower work add time at every story. Set a rate for each story and price runs on a lower roof at the lower rate.

How do I price gutter guards?

Per foot, on the same footage as the gutters, with a rate for each story. Give guards-only jobs their own minimum, because they are often short add-ons.

How many downspouts does a house need?

Enough to drain the roof for your local rainfall. SMACNA's method sizes them. For a bid, a count rule works: at least one downspout on each separate gutter, with one for every set number of feet or part of it and a minimum per job.

Can I measure gutter footage from an address?

Yes. Measured Bid measures the roof edges from aerial data and numbers each run. On 9 invoiced jobs its quoted footage had a median error of 14.2%, so confirm the runs on site before you order material.

Price gutter jobs from an address

Enter your rates once. Measured Bid measures the runs, counts downspouts and applies your story rates and minimums, in the dashboard or in a widget on your website.